Upcoming Event: Complete 2003 Robot & Complete 2007 Robot
UNIVERSITY NEIGHBORHOOD HIGH SCHOOL ROBOTICS
2007-2008 PRE SEASON CALENDAR >
GOALS-
2wks/bot
1. finish 03bot
2. finish 07bot
3. fundraising
TRAINING
1. drafting
2. mechanics
MONDAY
|
TUESDAY
|
WEDNESDAY
|
THURSDAY
|
FRIDAY
|
SAT
|
11/28/7
|
11/27/7
|
11/28/7
|
11/29/7
|
11/30/7
|
12/1/7
|
| |
|
|
Meeting 1. Arm extended 2". 2. Fundraising letter typed up. 3. Holes drilled into '07 bot to lighten it.
|
|
Meeting 1. Bolted teeth to arm. 2. Remounted compressor board. 3. Made tightening brackets for motor & gearboxes. 4. Tested drivetrain
|
|
MONDAY
|
TUESDAY
|
WEDNESDAY
|
THURSDAY
|
FRIDAY
|
SAT
|
12/24/6
|
12/25/6
|
12/26/6
|
12/27/6
|
12/28/6
|
12/29/6
|
WINTER RECESS
|
CHRISTMAS!
|
WINTER RECESS
|
WINTER RECESS
|
WINTER RECESS
|
WINTER RECESS
|
|
MONDAY
|
TUESDAY
|
WEDNESDAY
|
THURSDAY
|
FRIDAY
|
SAT
|
12/31/7
|
1/1/7
|
1/2/7
|
1/3/7
|
1/4/7
|
1/5/7
|
WINTER RECESS
|
NEW YEARS DAY
|
Meeting 1. Welcome back. 2. Cut spacers. 3. Reassemble arm. 4. Install motor assembly. 5. Ramp work. 6. Throw out old.
|
Meeting 1. Brainstorming practice. 2. Cleanup. 3. Throw out old material.
|
|
KICK-OFF @ Polytechnic University meet at UNHS @ 8:00am sharp
|
|
MONDAY
|
TUESDAY
|
WEDNESDAY
|
THURSDAY
|
FRIDAY
|
SAT
|
12/10/7
|
12/11/7
|
12/12/7
|
12/13/7
|
12/14/7
|
12/15/7
|
Meeting 1. Fixed motor assembly. 2. Installed air release valve. 3. Sent $5,000 to FIRST. 4. Fixed PWM cables.
|
|
Meeting 1. Solenoid now 12v. 2. Battery mount problem fixed. 3. Red light fixed. 4. Funding from both Credit Suisse & Verizon!
|
Meeting cancelled?
|
|
Meeting 1. Front teeth fixed. 2. Lowered front of arm. 3. Compressor platform bolted on. 4. Josh tested drivetrain. It works! '03 bot finished!
|
|
MONDAY
|
TUESDAY
|
WEDNESDAY
|
THURSDAY
|
FRIDAY
|
SAT
|
12/3/7
|
12/4/7
|
12/5/7
|
12/6/7
|
12/7/7
|
12/8/7
|
| |
|
|
Meeting 1. Compressor board renutted. 2. Fundraising letter heavily edited. 3. '07bot ramp hole-drilling. 4. Tested bot.
|
PAYMENTS DUE TO FIRST!
|
Meeting Cancelled
|
|
MONDAY
|
TUESDAY
|
WEDNESDAY
|
THURSDAY
|
FRIDAY
|
SAT
|
12/17/7
|
12/18/7
|
12/19/7
|
12/20/7
|
12/21/7
|
12/22/7
|
Meeting 1. Team practiced w/03bot 2. '07bot ramp design redrawn. 3. Elbow disassembly.
|
* Fundraising letter sent.
|
Meeting 1. People practiced with 03bot. 2. Started making new ramp. 3. 66t sprockets onto elbow. 4. Mapped ramp.
|
Meeting 1. Elbow reassembly problems. 2. Cut spacers. 3. Practiced with 03bot. 4. Dressed up '03 bot as Christmas bot. 5. Pizza & sandwichs
|
|
|
|